Data center development · Bhutan

Standardize the block.
Pre-sell the capacity.
Then build the next one.

bitit develops hydro-powered compute capacity in Bhutan. We take a site from power and permits through to an operating 100 MW block — then build the same block again, funding each phase from the one before it.

Developer, not a landlord 100 MW blocks Hydroelectric supply
Master plan: one template block replicated five times A hydroelectric supply feeds a substation, which distributes to six 100 megawatt blocks. Block 01 is the built template; blocks 02 through 06 are copies of it. HYDRO SUBSTATION BLOCK 01 100 MW TEMPLATE BLOCK 02 100 MW BLOCK 03 100 MW BLOCK 04 100 MW BLOCK 05 100 MW BLOCK 06 100 MW EACH BLOCK = 100 × 1 MW PODS
Built first — the template block Master plan — copies of the template

How the company works

A developer, not a landlord.

Most compute projects raise money, build a shell, and hope tenants arrive. We run the sequence in the other order — capacity is committed before the block is fully built, and each completed block pays for the ground under the next one.

  1. 01

    Secure the ground

    Land, grid interconnection, water, road access and the permits that let a block exist. This is the slow part, and it is the part that is worth owning.

  2. 02

    Standardize the block

    One design, 100 MW, assembled from a repeated 1 MW pod. Standardizing the pod is what makes the second block cheaper than the first, and the sixth cheaper than the second.

  3. 03

    Pre-sell before steel

    We target half a block committed before it goes to full build. A signed buyer is the cheapest financing available, and it is also the honest test of whether the capacity is wanted.

  4. 04

    Build the template, then copy it

    The first block absorbs the learning — the drawings, the vendors, the commissioning sequence. Everything after it is a copy, built by people who have built it before.

  5. 05

    Operate and collect

    Hosting fees on delivered capacity, billed against contracted load. Buyers own their machines; we own the building, the power and the uptime.

  6. 06

    Recycle the capital

    Cash from an operating block funds the next one rather than a dividend. The end state is an income-producing asset sold whole, not a company run forever.

Step 06 funds step 01 of the next block

The unit we sell

One hundred megawatts, sold whole.

A block is the smallest thing that makes sense to build twice. It is sized so a single buyer can take all of it, and structured so several buyers can share one without arguing about the walls.

Block capacity100 MW IT load
Smallest build increment1 MW pod
Pods per block100
Pilot ahead of the first full block20 MW
Commitment targeted before full build50 %
Power sourceHydroelectric grid supply
Sold asA whole block, or capacity within one
Buyer ownsMachines
bitit ownsBuilding, power, uptime

Figures describe the development standard. Commercial terms, tariff and delivery schedule are set per block and per buyer.

The site

Built where the power already is.

Bhutan generates its electricity almost entirely from hydropower. Siting compute next to that generation is the whole argument — it shortens the distance between the turbine and the rack, and it puts the load on a grid that was built for industry.

Generation

Predominantly hydroelectric, from run-of-river and storage schemes on Himalayan catchments.

Why it suits compute

Large, steady industrial loads are the kind of customer a hydro grid is easiest to plan around — and the kind that can be curtailed and restarted without breaking anything.

What we settle first

Interconnection, tariff and the licensing route are confirmed with the relevant authorities before a block is committed, not assumed from a brochure.

Development plan

Phase one is one block.

We would rather commission 20 MW that works than announce 600 MW that does not. The pilot exists to prove the pod design and the commissioning sequence at a size where mistakes are affordable.

Phase 1 · Pilot 20MW

Proves the 1 MW pod, the power path and the commissioning sequence. Small enough to correct, large enough to be a real reference.

Phase 1 · Template 100MW

The first complete block, taken to full build once commitment reaches the target. Everything learned here becomes the drawing set.

Phase 2 onward ×5blocks

Copies of the template, each sold whole, each funded substantially by the block before it.

Who we build for

Two kinds of buyer.

Operators who want their own capacity

Buyers who have outgrown rented compute and would rather hold the asset. They take a block, or a defined share of one, and keep their own machines inside it.

  • Takes a whole block or a fixed share
  • Owns the hardware, not the building
  • Contracted load, hosting fee against it

Latency-tolerant AI workloads

Work that cares about cost per delivered token far more than about the round trip to the user — batch inference, fine-tuning, rendering, anything queued rather than typed at.

  • Batch inference and offline scoring
  • Training and fine-tuning runs
  • Render and simulation queues

Contact

Tell us what you need powered.

Capacity enquiries, co-development, and everything else reach the same inbox. Say how much load and when, and you will get a straight answer about whether we can meet it.

support@bitit.sg